Aggie Company obtained a lease on August 1, 2018. The lease contract specifies a three-year primary term.

Question:

Aggie Company obtained a lease on August 1, 2018. The lease contract specifies a three-year primary term.

a. Drilling operations began on June 1, 2019, and continued until October 15, 2019, when the well was determined to be dry.

1) Would the first delay rental payment be required?

2) How many more delay rentals would be necessary to hold the lease without further drilling?

b. Assume drilling operations instead began on May 1, 2021, and the well was completed on October 12, 2021, as a producer.

1) Did the lease terminate on August 1, 2021? Explain.

2) How many years will the lease continue, assuming production in commercial quantities?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: