Which of the following items is not normally included in a project charter? a. the name of

Question:

Which of the following items is not normally included in a project charter?

a. the name of the project manager

b. budget information

c. stakeholder signatures

d. a Gantt chart

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: