Question: Seattle Boatbuilders was recently awarded a ($14,000,000) contract to construct a luxury liner for Cruiseliners Inc. Seattle estimates it will take 42 months to complete

Seattle Boatbuilders was recently awarded a \($14,000,000\) contract to construct a luxury liner for Cruiseliners Inc. Seattle estimates it will take 42 months to complete the contract.The company uses the cost-to-cost method to estimate profits.The following information details the actual and estimated costs for the years 2001-2004.

Year 2001 2002 2003 2004 Actual Cost- Current Year Estimated Cost to

Instructions:
1. Compute the revenue, cost, and gross profit to be recognized for each of the years 2001-2004 under the percentage-of-completion method.
2. Give the journal entries for each of the years 2001-2004 to record the information from (1).

Year 2001 2002 2003 2004 Actual Cost- Current Year Estimated Cost to Complete $6,800,000 $6,500,000 3,300,000 3,900,000 2,400,000 1,900,000 1,700,000

Step by Step Solution

3.39 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Intermediate Accounting Reporting Questions!