Question: A job order cost sheet for Standish Ltd is shown below: Job order no. 92 For 2000 units Date Direct Materials Direct Labour Manufacturing Overhead
A job order cost sheet for Standish Ltd is shown below:
Job order no. 92 | For 2000 units | ||
Date | Direct Materials | Direct Labour | Manufacturing Overhead |
Beg. bal. Jan. 1 | 7 000 | 8 000 | 5 200 |
5 | 5 000 | ||
12 | 7 000 | 4 900 | |
25 | 4 000 | ||
27 | 5 000 | 3 500 | |
$16 000 | $20 000 | $13 600 | |
Cost of completed job: | |||
Direct materials | $16 000 | ||
Direct labour | 20 000 | ||
Manufacturing overhead | 13 600 | ||
Total cost | $49 600 | ||
Unit cost ($49 600 / 2000) | $ 24.80 | ||
Required
A. What was the balance in Work in Process Inventory on 1 January if this was the only unfinished job? If manufacturing overhead is applied on the basis of direct labour cost, what overhead rate was used last year?
B. Prepare summary entries at 31 January to record the current year’s transactions pertaining to Job 92.
Step by Step Solution
3.26 Rating (152 Votes )
There are 3 Steps involved in it
A Work in Process Inventory on 1 January 20200 700080... View full answer
Get step-by-step solutions from verified subject matter experts