A job order cost sheet for Standish Ltd is shown below: Job order no. 92 For 2000
Question:
A job order cost sheet for Standish Ltd is shown below:
Job order no. 92 | For 2000 units | ||
Date | Direct Materials | Direct Labour | Manufacturing Overhead |
Beg. bal. Jan. 1 | 7 000 | 8 000 | 5 200 |
5 | 5 000 | ||
12 | 7 000 | 4 900 | |
25 | 4 000 | ||
27 | 5 000 | 3 500 | |
$16 000 | $20 000 | $13 600 | |
Cost of completed job: | |||
Direct materials | $16 000 | ||
Direct labour | 20 000 | ||
Manufacturing overhead | 13 600 | ||
Total cost | $49 600 | ||
Unit cost ($49 600 / 2000) | $ 24.80 |
Required
A. What was the balance in Work in Process Inventory on 1 January if this was the only unfinished job? If manufacturing overhead is applied on the basis of direct labour cost, what overhead rate was used last year?
B. Prepare summary entries at 31 January to record the current year’s transactions pertaining to Job 92.
Step by Step Answer:
Accounting
ISBN: 978-1118608227
9th edition
Authors: Lew Edwards, John Medlin, Keryn Chalmers, Andreas Hellmann, Claire Beattie, Jodie Maxfield, John Hoggett