Thornton Industries began construction of a warehouse on July 1, 2024. The project was completed on March

Question:

Thornton Industries began construction of a warehouse on July 1, 2024. The project was completed on March 31, 2025. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

Construction expenditures incurred were as follows:

The company’s fiscal year-end is December 31.


Required:
Calculate the amount of interest capitalized for 2024 and 2025.