Question: In a risk by process matrix, a process that helps to manage a risk indirectly would be shown to have: a. A key link. b.
In a risk by process matrix, a process that helps to manage a risk indirectly would be shown to have:
a. A key link.
b. A secondary link.
c. An indirect link.
d. No link at all.
Step by Step Solution
3.46 Rating (156 Votes )
There are 3 Steps involved in it
The correct answer is b A secondary link In a riskbyprocess matrix different processes are evaluated ... View full answer