A work center has the following open and planned orders for week 4. Calculate the total standard

Question:

A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).

Setup Time (hours) Order Run Time Total Time Quantity (hours/piece) (hours) Released Orders 120 300 1.00 0.10 340 200 2.