Back schedule the following shop order. All times are given in days. Move time between operations is

Question:

Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 200. Assume orders start at the beginning of a day and finish at the end of a day.

Queue Time (days) Operation Operation Time (days) Finish Work Center Arrival Number Date (a.m.) Date (p.m.) 110 3 10 120

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: