If sigma is 130 units, and the demand during the lead time is 250 units, calculate the

Question:

If sigma is 130 units, and the demand during the lead time is 250 units, calculate the safety stock and order point for:

a. A 50% service level.

b. An 85% service level.

Use the table in Figure 11.5 as help to calculate your answer.

Service Level (%) Safety Factor 50 0.00 75 0.67 80 0.84 85 1.04 90 1.28 1.56 94 95 1.65 96 1.75 1.88 97 98 2.05 99 2.33