Shop order 7777 is for 600 of part 8900. From the routing file, it is found that

Question:

Shop order 7777 is for 600 of part 8900. From the routing file, it is found that operation 20 is done on work center 300. The setup time is 3.5 hours, and run time is 0.233 hours per piece. What is the required capacity on work center 300 for shop order 7777?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: