Using the following product tree, determine the planned order receipts and planned order releases if 200 As are to be produced in week 5. All lead times are 1 week except for component E, which has a lead time of 2 weeks. D B E A C Part A Lead Time: 1 week Part B Lead Time: 1 week Week
Chapter 4, Problems #3
Using the following product tree, determine the planned order receipts and planned order releases if 200 As are to be produced in week 5. All lead times are 1 week except for component E, which has a lead time of 2 weeks.