What would be the reduction in manufacturing lead time if the second machine could not be set

Question:

What would be the reduction in manufacturing lead time if the second machine could not be set up until the setup was completed on the first machine?

An order for 100 of a product is processed on operation A. The setup time is 50 minutes, and the run time per piece is 9 minutes. Since this is a rush order, it is to be split into two lots of 50 each and run on two machines in the work center. The machines can be set up simultaneously.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: