Question: A project manager is executing a software development project whose scope was challenging to define upfront. Since the project had high change levels, success was
A project manager is executing a software development project whose scope was challenging to define upfront. Since the project had high change levels, success was achieved by breaking the effort into rapid short iterations called sprints of 2 to 4 weeks. The method adopted by the project manager is called:
A. Fast-tracking method of accelerating the project B. Adaptive life cycle or change-driven life cycle C. Discretionary dependency-driven model D. Portfolio management