Question: A PM started documenting high level risks which will help understand the potential threats and opportunities. Where should the PM look for the potential risks?

A PM started documenting high level risks which will help understand the potential threats and opportunities. Where should the PM look for the potential risks?

A. Risk Register B. Project Charter C. Stakeholder Register D. Communication plans