Question: A project manager is leading a Construction project in a faraway foreign land, and got a mail on site requesting details from the Environment and

A project manager is leading a Construction project in a faraway foreign land, and got a mail on site requesting details from the Environment and Pollution Board in the local Mandarin language. The PM then realized that they forgot to add an important foreign stakeholder at the beginning as they thought the vendor they are working with will take care of it. Now he is stuck. What do you suggest the project manager do next?

A. Inform the stakeholder that the documents are available only in English B. Avoid the request and continue working seeking support from the local vendor.

C. Escalate the issue to the project sponsor and seek help from him.

D. Add this new entity to the stakeholder register as an important category.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Accounting Questions!