Question: During a week a worker produced 300 units, working for 48 hours. The hourly rate is 40. The estimated time to produce a unit is
During a week a worker produced 300 units, working for 48 hours. The hourly rate is ₹40. The estimated time to produce a unit is 10 minutes. Under incentive scheme, 20 per cent additional time is allowed. Calculate his gross earnings under Halsey and Rowan Plans.
Step by Step Solution
3.37 Rating (153 Votes )
There are 3 Steps involved in it
Determination of Earnings of a Worker i Halsey Plan Hours worked x Rate per hour 50 Time saved x R... View full answer