Question: Recent supply chain issues has created problems for the project and the outsourced chip that was to come from China is expected to be delayed
Recent supply chain issues has created problems for the project and the outsourced chip that was to come from China is expected to be delayed significantly. This can delay the new Laptop under development release by three months or more. What PM should do?
A. Report this as an Enterprise Environmental Factor beyond your control.
B. Hire local chip vendors to deliver the same chip meeting design capacity and functionality meeting baselines.
C. Solicit proposals from local manufacturers that have ready items for delivery D. Ask Sponsor to increase budget and approve delays