Question: The PM is working on the project to complete development work on a construction project at a Budget of $1 Million. The Earned Value Analysis
The PM is working on the project to complete development work on a construction project at a Budget of $1 Million. The Earned Value Analysis shows 40% work is done 600K has already been spent. How much more will it cost to get the work done if cost performance remains unchanged?
A 1200000 B 892540 C 1600000 D 1492540