Question: The PM is working to Control procurements for the project and see that was done as per SOW, Agreement and contract signed. What is the
The PM is working to Control procurements for the project and see that was done as per SOW, Agreement and contract signed. What is the most important thing the PM should do?
A. Settle any pending Claims with ADR (Alternate Dispute Resolution)
B. Inspection of deliverables and Audit of whole process followed matches the SOW C. Closed Procurements Contract.
D. Administrative Closure with final payment of all pending invoices