Question: The project is being delivered using the Agile framework. The requirements are not clear and are ambiguous and the team went from last iteration to
The project is being delivered using the Agile framework. The requirements are not clear and are ambiguous and the team went from last iteration to the next one without discussing possible changes in backlog due to work done in last sprint and changing priorities. The PM decides to have Backlog Refinement meeting to solve this problem.What is the most important thing to do?
A. Update backlog, stories, and priorities, to keep backlog in ready state for next sprint B. Split large stories and size new stories to have realistic understanding C. Analyze dependencies and risks associated so that time is not wasted in next sprint D. Understand architecture details to review and reduce technical debt