Question: The project manager is planning the project schedule based on requirements baselined. After doing activity sequencing and estimating durations for all the activities, the project
The project manager is planning the project schedule based on requirements baselined. After doing activity sequencing and estimating durations for all the activities, the project manager has finally created a project timeline with the help of some key team members. Out of the following, which one is the most important to consider for the PM?
A. Project Schedule in milestone and gantt chart B. Schedule Baseline C. Schedule Data with histogram D. Project Calendar which is shiftwise