Question: This important project is starting and being worked upon and the PM is working on it along with the Sponsor. The sponsor asks a question:

This important project is starting and being worked upon and the PM is working on it along with the Sponsor. The sponsor asks a question: when are we going to finalize the Development approach for this project? What should the PM say?

A. The Charter stage B. Project Management Plan stage C. Business Requirements Documentation stage D. Execution phase.