Question: 1. The system that identifies and documents the functional and physical characteristics of a product or component is called: a. the change control system b.
1. The system that identifies and documents the functional and physical characteristics of a product or component is called:
a. the change control system
b. the configuration management system
c. change control meetings
d. expert judgmentÂ
2. Project planning has begun with your core team, and there is conflict on the sequence of the planning activities. From the list below which sequence is least likely to occur?
a. determine budget before estimate costs
b. qualitative risk analysis before quantitative risk analysis
c. plan procurements before conduct procurements
d. collect requirements before define scope