Question: Reserve analysis during the control risks process looks at: a. planned versus actual with respect to cost performance b. planned versus actual with respect to

Reserve analysis during the control risks process looks at:

a. planned versus actual with respect to cost performance

b. planned versus actual with respect to schedule performance

c. the amount of contingency reserve remaining versus the amount of risk remaining

d. the amount of money remaining versus the amount of work remaining