Question: Setting priority for future risk work is the objective of what process? a. plan risk management b. risk identification c. qualitative risk analysis d. plan
Setting priority for future risk work is the objective of what process?
a. plan risk management
b. risk identification
c. qualitative risk analysis
d. plan risk responses