Question: The most common type of simulation technique used to develop the schedule is: a. earned value method b. Monte Carlo Analysis c. decision tree analysis

The most common type of simulation technique used to develop the schedule is:

a. earned value method

b. Monte Carlo Analysis

c. decision tree analysis

d. expected monetary value