Question: The project plan should contain at least 3 baselines. Which baseline below is not typically one of the three? a. scope baseline b. risk baseline

The project plan should contain at least 3 baselines. Which baseline below is not typically one of the three?

a. scope baseline

b. risk baseline

c. schedule baseline

d. cost baseline