Question: You are conducting lessons learned on your project. The final SPI is 1.00. The final CPI is 1.12. There were 150 geographically dispersed team members.
You are conducting lessons learned on your project. The final SPI is 1.00. The final CPI is 1.12. There were 150 geographically dispersed team members. Although the customer accepted the final product, the customer has decided to shelve it.
Where might you have put more focus than you did?
a. managing the schedule
b. managing the budget
c. managing your team members
d. managing the relationships with the project stakeholders