Question: Your work on the project is expected to be constant for the six-month length of the project. During each month, your budget is $200. At
Your work on the project is expected to be constant for the six-month length of the project. During each month, your budget is $200. At the end of month four, you have 40% of the total work completed and you have spent 70% of your total budget. The project’s budget at completion for the project is:
a. $ 80
b. $ 140
c. $ 840
d. $1,200