Question: What is a direct materials quantity variance?
What is a direct materials quantity variance?
Step by Step Solution
3.46 Rating (162 Votes )
There are 3 Steps involved in it
A direct materials quantity variance is the difference between the actual quantity of materials used and the standard quantity of materials allowed for actual production multiplied by the standard price per material In equation form it is calculated as SP AQ Used SQ where SP the standard price allowed per unit of material ... View full answer