Sharp Company manufactures a product for which the following standards have been set: During March, the company

Question:

Sharp Company manufactures a product for which the following standards have been set:

image

During March, the company purchased direct materials at a cost of $55,650, all of which were used in the production of 3,200 units of product. In addition, 4,900 hours of direct labour time was worked on the product during the month. The cost of this labour time was $36,750. The following variances have been computed for the month:

Materials quantity variance........................$4,500 UTotal labour variance.....................................2,000 FLabour efficiency variance............................1,000 U

Required:

1. For direct materials:

a. Compute the actual cost per metre for materials for March.

b. Compute the materials price variance and a total variance for materials.

2. For direct labour:

a. Compute the standard direct labour rate per hour.

b. Compute the standard hours allowed for the month?s production.

c. Compute the standard hours allowed per unit of product.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction to Managerial Accounting

ISBN: 978-1259105708

5th Canadian edition

Authors: Peter C. Brewer, Ray H. Garrison, Eric Noreen, Suresh Kalagnanam, Ganesh Vaidyanathan

Question Posted: