Question: The project team is working on creating a software which can identify personal identification information or PII inside a file saved on PC. The project
The project team is working on creating a software which can identify personal identification information or PII inside a file saved on PC. The project is currently in the execution phase. Which of the following represents the work performance data?
A. Story points completed B. List of stakeholders C. Actual cost incurred D. Number of defects
Step by Step Solution