Question: The project charter is: A. The initial project plan until the formal one is developed. B. Signed by the project manager. C. Symbolic only with
The project charter is:
A. The initial project plan until the formal one is developed.
B. Signed by the project manager.
C. Symbolic only with no real authorization properties.
D. The project’s first official project document.