Question: While planning the JKL Project, you bring together the software development team coaches as well as the control account managers to create the consolidated plan
While planning the JKL Project, you bring together the software development team coaches as well as the control account managers to create the consolidated plan of the entire hybrid project. The coaches are bringing their release plans and backlogs to the meeting; what will the control account managers bring?
A. Work breakdown structure, Activity list.
B. The JKL project scope statement.
C. The JKL S-curve.
D. The JKL project charter.