Question: You are assigned to replace a project manager on a large software project for a telecommunications company in the middle of executing the work. Portions
You are assigned to replace a project manager on a large software project for a telecommunications company in the middle of executing the work. Portions of the software are being supplied by subcontractors working at your company’s offices. You would like to know what performance metrics are going to be tracked for these contract workers. Where could you find such information?
A. The project charter.
B. The procurement management plan.
C. The WBS.
D. The organizational process assets.