Question: Your agile development organization is submitting a proposal for a contract that is well aligned with its expertise. However, the contract that is out for
Your agile development organization is submitting a proposal for a contract that is well aligned with its expertise. However, the contract that is out for bid is from a government entity that your organization has not worked with in the past. The government entity places a favorable weighting on those companies headquartered in the capitol. So, your team has partnered with a small company there to offer a joint proposal. In terms of risk strategies, this scenario describes the use of which one?
A. Transfer.
B. Exploit.
C. Share.
D. Mitigate.