Question: A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path is compressed to 8 weeks, then: a. We

A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path is compressed to 8 weeks, then:

a. We now have two critical paths

b. The 9-week path is now the critical path

c. Only the 7-week path has slack

d. Not enough information is provided to make a determination