Question: If BAC = $24,000, BCWP = $12,000, ACWP = $10,000, and CPI = 1.2, then the cost that remains to finish the project is: a.

If BAC = $24,000, BCWP = $12,000, ACWP = $10,000, and CPI = 1.2, then the cost that remains to finish the project is:

a. $10,000

b. $12,000

c. $14,000

d. Cannot be determined