Question: If BCWS = 1,000, BCWP = 1,200, and ACWP = 1,300, the project is: a. Ahead of schedule and under budget b. Ahead of schedule

If BCWS = 1,000, BCWP = 1,200, and ACWP = 1,300, the project is:

a. Ahead of schedule and under budget

b. Ahead of schedule and over budget

c. Behind schedule and over budget

d. Behind schedule and under budget