Question: If BCWS = 1,000, BCWP = 1,200, and ACWP = 1,300, the project is: a. Ahead of schedule and under budget b. Ahead of schedule
If BCWS = 1,000, BCWP = 1,200, and ACWP = 1,300, the project is:
a. Ahead of schedule and under budget
b. Ahead of schedule and over budget
c. Behind schedule and over budget
d. Behind schedule and under budget