Question: One technique for risk evaluation uses a questionnaire, a series of rounds, reports submitted in confidence and then circulated with the source unidentified. If the

One technique for risk evaluation uses a questionnaire, a series of rounds, reports submitted in confidence and then circulated with the source unidentified. If the project manager uses this technique, he/she is using:

a. The Delphi Technique

b. The Work Group

c. Unsolicited team responses

d. A risk management team