Question: PM Quick Check: Before developing the project cost estimates for resources the project manager should consider the following organizational expense items: building maintenance, fringe benefits,

PM Quick Check: Before developing the project cost estimates for resources the project manager should consider the following organizational expense items:

building maintenance, fringe benefits, group insurance, office supplies, clerical support, postage, retirement plans, sick leave, vacation pay. These items are generally associated with:

a. Contractor direct costs

b. Overhead rates or costs

c. Variable costs

d. External costs