Question: When substantial changes to the project schedule have occurred, which of the following might you perform to provide a new means of measuring performance? A.
When substantial changes to the project schedule have occurred, which of the following might you perform to provide a new means of measuring performance?
A. Rebaselining B. Schedule revision C. Schedule update D. Schedule change