Question: While sequencing activities, a project manager decides to utilize the precedence diagramming method to show existing dependencies between activities. Which of the logical relationships is

While sequencing activities, a project manager decides to utilize the precedence diagramming method to show existing dependencies between activities. Which of the logical relationships is the project manager most likely to use?

A. Finish-to-start B. Start-to-finish C. Finish-to-finish D. Start-to-start