Question: You re in the process of developing a project schedule for a new project for which you ve just completed the WBS. What
You ’ re in the process of developing a project schedule for a new project for which you ’ ve just completed the WBS. What would be the smart next step in figuring out what tasks go into the project schedule?
A. Develop an activity list.
B. Determine the critical path tasks.
C. Develop a network diagram.
D. Estimate activity duration.