Question: Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000, with

Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000, with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend?

A. Either Project A or Project B, because the payback periods are equal B. Project A, because Project B’s payback period is 21 months C. Project A, because Project B’s payback period is 24 months D. Project A, because Project B’s payback period is 20 months

Step by Step Solution

There are 3 Steps involved in it