Question: 74. When a project can be completed in a number of completely different ways that might involve branching after performing activities, the best schedule and

74. When a project can be completed in a number of completely different ways that might involve branching after performing activities, the best schedule and control technique would be

a. Program Evaluation and Review Technique.

b. Gant chart.

c. Critical Path Method.

d. Graphical Evaluation and Review Technique.