Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path.

Question:

Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path.


Problem and Exercise 3-45.

Assume that you have a project with seven activities labeled A–G (below). Derive the earliest completion time (or early finish—EF), latest completion time (or late finish—LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Draw a Gantt chart for these tasks.

Preceding Expected Duration Event Critical EF LF Slack Path? Activity A 5 B A 3 A 4 D E В, С 4 1 G D, E, F 5

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Modern Systems Analysis And Design

ISBN: 9780134204925

8th Edition

Authors: Joseph Valacich, Joey George

Question Posted: