Question: 8. The CPM network below represents a project with the times estimated in weeks. a. What is the expected project duration? b. What is the
8. The CPM network below represents a project with the times estimated in weeks.
a. What is the expected project duration?
b. What is the critical path?
c. Find the ES, EF, LS, LF, and float at each activity

C, 10 E, 12 H, 8 L9 A,5 B, 3 F,9 4, 6 K,7 N, 2 D, 7 G, 9 7,8 M, 6
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
