Question: 8. The CPM network below represents a project with the times estimated in weeks. a. What is the expected project duration? b. What is the

8. The CPM network below represents a project with the times estimated in weeks.

a. What is the expected project duration?

b. What is the critical path?

c. Find the ES, EF, LS, LF, and float at each activity