Question: Consider a process assembling shopping carts. The process starts with a unit cost of $20 for the first unitthat is, c(1) = 20and a learning

Consider a process assembling shopping carts. The process starts with a unit cost of $20 for the first unit—that is, c(1) = 20—and a learning rate of LR = 0.95. What will be the unit costs for the 29th unit?