Question: Consider a worker-paced line with three process steps, each of which is staffed with one worker. The sequence of the three steps does not matter
Consider a worker-paced line with three process steps, each of which is staffed with one worker.
The sequence of the three steps does not matter for the completion of the product. Currently, the three steps are operated in the following sequence.
![Activity Time [min/unit] Step 1 3 BAN Step 4 Step 5](https://dsd5zvtm8ll6.cloudfront.net/images/question_images/1708/6/9/2/78365d8952f3bbe01708692782498.jpg)
a. What would happen to the inventory in the process if the process were operated as a push system?
b. How would you implement a pull system?
Activity Time [min/unit] Step 1 3 BAN Step 4 Step 5